Stage 4 Fire Strategy - Technical Design
Introduction
A Stage 4 fire strategy is the technical-design version of the fire strategy.
RIBA Stage 4 is Technical Design. The outcome should be completion of the design information required to manufacture and construct the building.
The Stage 4 strategy should therefore move beyond broad principles and coordinated intent. It should be supported by complete specifications, calculations, schedules, drawings and specialist designs.
Purpose
The Stage 4 strategy should:
- Complete the fire safety technical design
- Embed the strategy into construction and manufacturing information
- Close the design risks identified at Stage 3
- Coordinate design-team and specialist-subcontractor information
- Define testable requirements
- Support the Building Regulations application
- Establish how changes and substitutions will be controlled
- Define the evidence required to demonstrate compliant construction
- Provide a clear basis for commissioning and handover
A Stage 4 strategy should not rely on site teams to resolve fundamental design decisions.
Required Inputs
The Stage 4 design should use:
- Approved Stage 3 fire strategy
- Coordinated architectural and engineering design
- Fire strategy plans and compartmentation drawings
- Confirmed occupancy and evacuation assumptions
- Final structural design
- Final façade design
- Specialist smoke-control design
- Specialist fire alarm design
- Specialist sprinkler or suppression design
- Lift and vertical transportation design
- Emergency lighting design
- Door and hardware schedules
- Firestopping and penetration strategy
- Procurement and contractor proposals
- Insurer and warranty requirements
- Building control or BSR comments
- Change-control requirements
- Stage 4 responsibility matrix
Technical Design Requirements
Means of Escape
The Stage 4 package should complete:
- Final escape route dimensions
- Final exit and stair capacities
- Door swings and clear widths
- Escape hardware
- Security release arrangements
- Stair and lobby construction
- Refuge details
- Evacuation lift design
- Final exit arrangements
- External escape route construction
- Escape signage
- Emergency lighting design
- Wayfinding requirements where applicable
- Final management limitations affecting use or occupancy
Compartmentation and Passive Fire Protection
The technical design should define:
- Wall and floor types
- Fire-resistance classifications
- Junction details
- Head-of-wall details
- Movement-joint details
- Service penetration details
- Linear gap seals
- Firestopping systems
- Cavity barriers
- Façade perimeter fire barriers
- Roof void barriers
- Fire and smoke dampers
- Access panels
- Fire-resistant glazing
- Fire curtain and shutter details
- Installation tolerances and substrate requirements
- Inspection and evidence requirements
Generic notes such as “firestop all penetrations” are not sufficient technical design.
Fire Doors
The Stage 4 design should coordinate:
- Door identification
- Required fire and smoke rating
- Door construction and certification route
- Frame and seal requirements
- Self-closing requirements
- Hold-open or swing-free devices
- Access-control hardware
- Escape hardware
- Automatic release arrangements
- Thresholds and undercuts
- Glazing
- Signage
- Ironmongery compatibility
- Installation and inspection requirements
Structural Fire Safety
The package should complete:
- Fire-resistance specifications
- Protection thicknesses or systems
- Connection and junction requirements
- Structural fire engineering calculations
- Fire-protection interfaces with services and façades
- Inspection and quality-assurance requirements
- Design assumptions that must be preserved during construction
External Walls and Roofs
The technical design should define:
- Complete wall build-ups
- Product classifications
- Insulation and sheathing
- Cavity barriers
- Slab-edge fire barriers
- Window and curtain-wall interfaces
- Balconies and attachments
- Fixings and support systems
- Fire performance evidence
- Roof coverings
- Roof and wall junctions
- Interfaces with compartment walls and floors
- Installation inspection requirements
Active Fire Protection Technical Design
Fire Detection and Alarm
The Stage 4 fire alarm design should normally include:
- Confirmed system category and objectives
- Device and system performance specifications
- Detection coverage
- Detector types and modes
- Fire detection zones
- Alarm zones
- Control and indicating equipment
- Network architecture
- Loop and circuit design
- Short-circuit isolation
- Sound pressure design
- Visual alarm coverage
- Voice alarm design where applicable
- Alarm transmission
- Power-supply and standby calculations
- Cable type and routing requirements
- Survivability and segregation
- Interface design
- Monitoring requirements
- Device schedules
- Layout drawings
- Zone plan requirements
- Commissioning and witness-test requirements
- Final cause-and-effect matrix
BS 5839-1:2025 requires the system design to support the evacuation strategy, identifies the need for defined responsibilities, and requires completed documentation including as-fitted drawings, certificates and a cause-and-effect matrix or text description.
Smoke Control
The Stage 4 smoke-control design should include:
- Final design basis
- Design fire assumptions
- Calculations and modelling
- Fan and vent duties
- Shaft, duct and damper details
- Replacement-air design
- Pressure differential calculations
- Environmental ratings
- Power supplies and controls
- Detection and initiation
- Firefighter controls
- Monitoring and feedback
- Cause-and-effect logic
- Control panel and interface details
- Maintenance access
- Commissioning procedures
- Performance test and acceptance criteria
Sprinklers and Suppression
The Stage 4 design should include, as applicable:
- Final design standard
- Hazard classification
- Hydraulic calculations
- Water supply
- Tank and pump design
- Valve and zoning arrangement
- Pipework design
- Head or nozzle layout
- Monitoring
- Fire alarm interfaces
- Release logic
- Abort and manual controls
- Warning devices
- Room integrity requirements
- Venting and pressure relief
- Commissioning and acceptance tests
- Maintenance access and isolation strategy
Detailed Cause-and-Effect Matrix
The Stage 4 cause-and-effect matrix should be detailed enough to:
- Configure and program the systems
- Coordinate all interfaces
- Commission each function
- Witness the integrated system test
- Train the building operator
- Form part of the handover information
The Matrix Should Identify
- Input reference, address or clearly defined functional group
- Input type
- Input location or zone
- Operating condition
- Alarm stage
- Output reference or group
- Required action
- Delay
- Coincidence or dependency
- Latching and reset behaviour
- Manual override
- Disablement behaviour
- Fault response
- Required confirmation or feedback
- Interface owner
- Drawing or specification reference
- Test and acceptance requirement
Typical Input Conditions
- Manual call point
- Smoke detector
- Heat detector
- Multi-sensor detector
- Aspirating system alarm levels
- Beam detector
- Sprinkler flow
- Sprinkler valve tamper
- Suppression first-stage and confirmed alarm
- Smoke-control detector or switch
- Firefighter control
- Evacuation control
- Plant or process fire signal
- Common fire, common fault or system-specific signal
Typical Output Actions
- Evacuate
- Alert
- Staff alarm
- Voice message
- Visual alarm
- Alarm receiving centre transmission
- Smoke-control fan or vent operation
- Damper operation
- Door release or closure
- Access-control release
- Lift recall or grounding
- Evacuation lift operation
- HVAC shutdown or mode change
- Gas or fuel isolation
- Fire curtain or shutter operation
- Suppression release
- Wayfinding or signage change
- Fire-service indication
- BMS indication
Avoid Ambiguous Entries
Entries such as the following are not sufficiently testable:
- “Operate as required”
- “All associated doors”
- “Smoke control to run”
- “Lifts to respond”
- “Signal to BMS”
- “General alarm where necessary”
Each action should identify the exact intended state, scope, timing and responsible interface.
Interface Schedule
Complex projects should use an interface schedule alongside the cause-and-effect matrix.
The schedule should identify:
- System providing the signal
- System receiving the signal
- Interface location
- Signal type
- Normal and alarm state
- Fail-safe state
- Cable and monitoring responsibility
- Power-supply responsibility
- Terminal or protocol requirements
- Required feedback
- Testing responsibility
- Witnessing responsibility
- Final documentation owner
This prevents a gap where both contractors assume the other is providing the interface.
What Should Develop Alongside the Stage 4 Strategy?
| Document or activity | Stage 4 purpose |
|---|---|
| Final architectural details | Provide construction details for escape routes, compartments, doors and shafts. |
| Final specifications | Define performance, materials, installation and acceptance requirements. |
| Fire door schedule | Coordinates every fire door and its hardware, controls and certification. |
| Passive fire protection details | Define firestopping, cavity barriers, dampers and junctions. |
| Façade technical fire information | Defines final build-ups, barriers, fixings and evidence. |
| Fire alarm design package | Provides layouts, calculations, schedules, specifications and cause and effect. |
| Smoke-control design package | Provides calculations, schematics, controls and commissioning requirements. |
| Sprinkler or suppression design | Provides calculations, layouts, water supplies and interfaces. |
| Emergency lighting design | Provides layouts, calculations, supplies and test requirements. |
| Lift fire strategy design | Defines recall, firefighting and evacuation lift functions. |
| Detailed cause-and-effect matrix | Provides the testable integrated operating sequence. |
| Interface schedule | Allocates every cross-system signal and responsibility. |
| Commissioning plan | Defines individual and integrated testing. |
| Inspection and test plan | Defines construction inspections and evidence capture. |
| Building Regulations application | Demonstrates the completed design route to compliance. |
| Change control plan | Controls changes to the approved or agreed design. |
| Construction control plan | Defines how compliant work and as-built evidence will be achieved and recorded. |
| Regulation 38 information plan | Defines the content, format and ownership of handover information. |
Higher-Risk Buildings
For higher-risk building work in England, Stage 4 may need to support submission of:
- Drawings and plans
- Building Regulations compliance statement
- Change control plan
- Construction control plan
- Competence declaration
- Fire and emergency file
- Mandatory occurrence reporting plan
- Partial completion strategy where relevant
The fire and emergency file is often known as a fire strategy and must explain how the design provides:
- Means of escape and warning
- Internal fire-spread control
- External fire-spread control
- Fire-service access and facilities
- Management and maintenance arrangements relevant to emergency evacuation
The design should be sufficiently complete for approval and should not depend on unresolved construction-stage design.
Change Control
Any proposed change that may affect the fire strategy should be reviewed before implementation.
Examples include changes to:
- Occupancy or use
- Stairs and escape routes
- Compartmentation
- Fire-resistance periods
- Fire doors
- Façade materials or build-ups
- Cavity barriers
- Fire alarm category or coverage
- Cause and effect
- Smoke-control systems
- Sprinkler or suppression systems
- Firefighting shafts or lifts
- Evacuation lifts
- Product specifications
- Service routes and penetrations
- Management assumptions
The review should identify:
- Which strategy assumptions are affected
- Which drawings and specifications require revision
- Whether regulatory approval is required
- Whether calculations must be repeated
- Whether the cause-and-effect matrix must change
- Whether commissioning and test plans must change
- How the change is recorded in the golden thread or project information system
Inspection, Testing and Evidence
The Stage 4 design should specify the evidence required during construction.
This may include:
- Product and system certification
- Installation records
- Photographic evidence
- Location-tagged inspection records
- Firestopping records
- Door inspection records
- Damper inspection records
- Façade cavity-barrier records
- Pressure and flow test results
- Electrical test results
- Fire alarm design, installation and commissioning certificates
- Cause-and-effect test records
- Integrated systems testing
- Smoke-control performance tests
- Sprinkler and suppression test records
- Witnessing and sign-off requirements
- Red-line and as-built drawing requirements
Evidence should be captured while work remains visible and accessible.
Stage 4 Deliverables
A typical Stage 4 fire safety package may include:
- Stage 4 technical fire strategy
- Final fire strategy drawings
- Final compartmentation drawings
- Final fire-resistance and fire door schedules
- Passive fire protection details
- Structural fire design and specifications
- Façade fire technical package
- Fire alarm technical design
- Detailed cause-and-effect matrix
- Interface schedule
- Smoke-control technical design
- Sprinkler or suppression technical design
- Emergency lighting design
- EVC and evacuation lift design
- Firefighting facilities details
- Final specifications
- Commissioning and integrated testing plan
- Inspection and test plan
- Building Regulations application information
- Change-control requirements
- Regulation 38 and as-built information requirements
Stage 4 Completion Criteria
Stage 4 should not be considered complete until:
- All design information required for manufacture and construction is complete
- Specialist designs are coordinated
- Fundamental assumptions have been closed or formally controlled
- Means of escape is fully detailed
- Passive fire protection is buildable and specified
- Active system designs are complete
- The cause-and-effect matrix is testable
- Interfaces and responsibilities are defined
- The Building Regulations submission is supported by coordinated information
- Design alternatives and substitutions have an approval process
- Inspection, commissioning and evidence requirements are defined
- Regulation 38 and as-built requirements are planned
- Residual operational restrictions are clearly recorded
Common Failures
- Reissuing the Stage 3 report and calling it Stage 4
- Leaving specialist design until Stage 5
- Missing penetration, junction and cavity-barrier details
- Allowing contractor design without performance requirements
- Incomplete fire alarm coverage or sound pressure design
- A cause-and-effect matrix that cannot be commissioned
- Interfaces with no identified owner
- Smoke-control calculations that do not match the final architecture
- Product substitutions accepted without fire strategy review
- No integrated testing plan
- No plan for as-built evidence
- Treating Building Regulations approval as a substitute for design coordination
After Stage 4
During construction and handover, the Stage 4 strategy should be maintained as a controlled document.
It should be updated to reflect:
- Approved design changes
- Accepted contractor proposals
- Final installed systems
- Final cause-and-effect programming
- Commissioning results
- As-built drawings
- Variations and residual risks
- Management and maintenance requirements
The final as-built fire strategy and supporting information should be handed to the person responsible for operating the building.
BS 5839-1:2025 requires completed fire alarm documentation to include relevant certificates, operation and maintenance information, as-fitted drawings, cause-and-effect information, a logbook and records of agreed variations.
Return to Fire Strategies.
Important: A Stage 4 strategy should be supported by complete and coordinated technical design. Any unresolved item should be clearly identified, allocated and controlled rather than silently transferred to construction.
Fire Secure UK